NEW QUESTION # 63
Revenues & Payment
Your customer wants to plans and post revenues for WBS elements.
What is crucial for the implementation of revenues planning and posting for WBS elements?.

  • A. Revenue planning and billing must be activated in the corresponding network type.
  • B. At least one WBS element must be a billing element.
  • C. A sales order item has to be assigned to each WBS element used for revenue planning.
  • D. The indicator "Project type" must be set to "Customer project".

Answer: B


NEW QUESTION # 64
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

  • A. The scheduling parameters for the network
  • B. The table of MRP controllers
  • C. The control key
  • D. The network profile

Answer: A


NEW QUESTION # 65
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

  • A. None
  • B. Individual overview capacity requirements
  • C. Structure overview
  • D. Extended capacity evaluation
  • E. Capacity load work center view

Answer: B


NEW QUESTION # 66
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?

  • A. Enter 10 days as duration
  • B. Enter an offset of 10 days to the start date of the activity
  • C. Enter February 10 as fixed date
  • D. Enter an offset of -18 days to the finish date of the activity

Answer: C

Explanation:
To define a milestone for February 10 that should not be changed through scheduling, you should enter February 10 as fixed date for the milestone. A fixed date is a date that remains unchanged during scheduling, regardless of any changes in the dates of preceding or succeeding activities or milestones. A fixed date can be entered manually or automatically derived from a constraint. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 67
Which report can use user-specific layouts?

  • A. Hierarchical report
  • B. Line item report
  • C. Cost element report
  • D. Enhanced individual overview

Answer: B

Explanation:
A line item report is a report type that can use user-specific layouts. A line item report displays detailed information on individual cost or revenue elements for project objects, such as WBS elements or activities. You can use user-specific layouts to define which fields are displayed or hidden, how they are sorted or filtered, and how they are totaled or subtotaled. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 68
Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers to this question.

  • A. Sources can be based on line items
  • B. Usage of cost elements is mandatory
  • C. Sales prices are maintained in the DIP profile
  • D. DIP is used to create a quotation
  • E. Material determination is mandatory

Answer: A,C,E

Explanation:
Dynamic item processor (DIP) is a tool that allows you to create sales order items automatically based on project data. Some of the features of DIP are: Sales prices are maintained in the DIP profile, which is a parameter that defines how sales order items are created and priced from project data. Sources can be based on line items, which means that you can use individual cost elements or revenue elements as sources for creating sales order items. Material determination is mandatory, which means that you have to assign a material number to each source in order to create sales order items. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 69
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.

  • A. Project versions can be created automatically based on user status.
  • B. Project versions are mandatory for Milestone Trend Analysis (MTA).
  • C. Manually created project versions always require a project version profile.
  • D. Project versions can be changed.

Answer: B,D


NEW QUESTION # 70
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question

  • A. If the reduction strategy is set in each activity
  • B. If the reduction strategy is set in the network header
  • C. If the appropriate reduction type is set in the parameters for network scheduling
  • D. If the maximum reduction level is less than 100

Answer: C,D


NEW QUESTION # 71
Resources
How can you define external task in your project.
Note : there are 2 correct answers for this question.

  • A. Create an external activity in a network.
  • B. Create a service activity in a network.
  • C. Create a service milestone.
  • D. Assign a purchase order for external processing to the project definition.

Answer: A,B

Explanation:
"You can create external activities in a network to represent tasks that are performed by external service providers or vendors." According to SAP Press4, "You can create service activities in a network to represent tasks that are performed by internal service providers." Reference: 4


NEW QUESTION # 72
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.

  • A. Recording of external services in the service entry sheet
  • B. Goods receipt of a non-stock item
  • C. Goods receipt into unvaluated project stock
  • D. Goods receipt into valuated project stock

Answer: A,C


NEW QUESTION # 73
Which object is used to allocate the costs from a claim to the project structure?

  • A. Internal order
  • B. Network activity
  • C. Claim
  • D. WBS element

Answer: B


NEW QUESTION # 74
Float time is calculated during scheduling.
Which of the following statements about float time are correct?
Note: There are 3 correct answers to this question

  • A. By default, critical activities have a float time, which is less than or equal to zero
  • B. Activities with the time constraint "Must start on" always have a negative float time
  • C. Float time can be negative
  • D. The float time of WBS elements is calculated by extrapolation
  • E. The maximum size of a free float is as large as the total float of an activity

Answer: B,C,E


NEW QUESTION # 75
When you create a service activity in your network, what data can be entered? Note: There are 3 correct Answers to this question.

  • A. Service specification
  • B. Overall limit (maximum value of all unplanned services)
  • C. Material master within service specification
  • D. Service purchase order number
  • E. Vendor

Answer: A,B,E


NEW QUESTION # 76
Which statement is valid regarding networks?

  • A. Material components can be assigned to activity elements
  • B. A network activity can be assigned to several WBS elements
  • C. A network can be activity-account-assigned and header-account-assigned
  • D. Relationships can be used to connect activities of different networks

Answer: B


NEW QUESTION # 77
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct answers to this question

  • A. Sales order
  • B. Quotation
  • C. Inquiry
  • D. Billing

Answer: A,D

Explanation:
Sales order and billing are some of the sales documents that can update planned revenues on WBS elements. Sales order is a document that records a customer's request for goods or services from a sales organization. Billing is a document that records the delivery of goods or services to a customer and requests payment for them. Both sales order and billing can update planned revenues on WBS elements if they are assigned to them directly or indirectly via network activities. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 78
Resources
You Want assign milestone to WBS element? For what can you use these milestone.

  • A. For trend analysis.
  • B. To set an actual finish date for WBS element-
  • C. To start workflow task.
  • D. To create standard network

Answer: A


NEW QUESTION # 79
What could be a reason to use expert mode in the valuation method for results analysis?

  • A. Valuation in different currencies
  • B. Usage of different line ID
  • C. Assignments of different accounts for postings to financial accounting
  • D. Billing WBS elements belonging to different company codes

Answer: B

Explanation:
One reason to use expert mode in the valuation method for results analysis is usage of different line ID. Results analysis is a function that allows you to calculate and post values for work in process (WIP), reserves for unrealized costs (RUC), profit from sales order stock (PSOS), and so on. Results analysis uses valuation methods to determine how these values are calculated based on various criteria, such as cost of sales method, percentage of completion method, revenue-based method, and so on. Expert mode is a type of valuation method that allows you to define your own logic and rules for results analysis by using formulas and conditions. One reason to use expert mode in the valuation method for results analysis is usage of different line ID. A line ID is a parameter that identifies a line item in results analysis data. A line ID can have various attributes, such as cost element group, value category, posting indicator, and so on. By using expert mode in the valuation method for results analysis, you can use different line ID for different scenarios or requirements that are not covered by the standard valuation methods. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 80
Project Structure
You plan double the work on each internal activity for multiple project. What do you recommend?

  • A. Double the work of each internal activity, one after another, in the project Builder.
  • B. Use mass change within the project Builder (CJ20N).
  • C. Use mass change (CNMASS) in the project system.
  • D. Double the capacity in the work center.

Answer: C

Explanation:
Mass change (CNMASS) is a powerful tool that allows you to change multiple fields in multiple objects at once. You can use it to change fields in project definitions, WBS elements, networks, activities, milestones, and PRTs." Reference: 3


NEW QUESTION # 81
......


SAP C-TS412-2021 certification exam is a valuable credential for individuals interested in demonstrating their expertise in project management using SAP S/4HANA. With the right preparation and study materials, candidates can successfully pass C-TS412-2021 exam and earn this highly respected certification.

 

Latest C-TS412-2021 Actual Free Exam Questions Updated 112 Questions: https://www.passtestking.com/SAP/C-TS412-2021-practice-exam-dumps.html

Attested C-TS412-2021 Dumps PDF Resource [2024]: https://drive.google.com/open?id=1cOAUcjGRKaWyhtWZyZzR0msXHbYXu7rz