PMI Risk Management Professional - PMI-RMP Exam Practice Test
A project manager is leading a complex, high-risk construction project in the city center. To address risk based on lessons learned from similar past building projects, the risk manager assigns a team member to assess and confirm risk thresholds for the project.
What should the risk manager do?
What should the risk manager do?
Correct Answer: B
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.
How should the risk manager improve collaboration during risk planning?
How should the risk manager improve collaboration during risk planning?
Correct Answer: B
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
A company in the mining industry accommodates a lot of innovation and changing work conditions. Because of this, the company experiences difficulty in predicting long term business plans.
How should a professional risk manager manage the risks in such situations?
How should a professional risk manager manage the risks in such situations?
Correct Answer: A
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?
Correct Answer: B
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
A risk manager monitors risks on a medium-sized project by collecting inputs and data from individual project team members. What output is produced by the risk manager after analyzing the information they receive?
Correct Answer: A
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
A project manager has requested the risk manager ' s support in deciding whether to purchase a new component to expedite project execution. The component price is US$100,000 and there is a 30% chance that it might not function as expected resulting in an additional US$50,000 cost However, if the component does work well the project will make a profit of USS500.000. If the component is not purchased, there is an 80% chance of failure with an impact of US$250 000.
What should the risk manager recommend?
What should the risk manager recommend?
Correct Answer: A
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.
Which risk response strategy is the program manager using in this scenario?
Which risk response strategy is the program manager using in this scenario?
Correct Answer: C
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
An organization is embarking on a multi-million-dollar project with numerous identified risks. What should the project risk team do to navigate the risks on this project?
Correct Answer: D
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
The trigger for a highly categorized threat has occurred. The risk has a set response plan.
Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?
Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?
Correct Answer: A
Vote an answer
A risk manager and project team are managing a software system project, which is expected to be completed within 12 months. The project is currently halfway through, and the team has just delivered the second version of the prototype. During the weekly status meeting, a team member reported that an important stakeholder is facing an issue, which will likely result in a change request that is outside the scope of the current prototype.
What should the risk manager advise the team to do first?
What should the risk manager advise the team to do first?
Correct Answer: D
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project ' s risk management activities? (Choose 3)
Correct Answer: A,B,D
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.
What is the current project risk exposure?
What is the current project risk exposure?
Correct Answer: A
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
While developing a risk management plan for a complex program in a metricized environment, a program management team is itemizing a response plan for each identified risk that appears in the risk register. What should the risk manager do to effectively monitor the risks?
Correct Answer: B
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.
How should the risk manager interpret such a low CPI value?
How should the risk manager interpret such a low CPI value?
Correct Answer: C
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).