PRINCE2 (Projects IN Controlled Environments) is a project management methodology that is widely adopted by organizations across the world. It provides a structured approach to managing projects and is considered one of the best project management frameworks available. PRINCE2 Foundation is the entry-level certification in the PRINCE2 certification path. PRINCE2 7 Foundation written Exam certification exam tests the candidate’s knowledge of the PRINCE2 methodology, principles, themes, and processes.


The PRINCE2 Foundation exam is the entry-level certification in the PRINCE2 certification path. It is designed for individuals who are new to project management or wish to enhance their skills in project management. PR2F exam covers the fundamental principles of the PRINCE2 methodology, including the seven principles, themes, and processes. PR2F exam is a closed-book exam that consists of 60 multiple-choice questions, and the candidate is required to score 55% or higher to pass.

 

NEW QUESTION # 256
Which is a minimum requirement for applying the organization theme?

  • A. The project's approach to engaging with its stakeholders must be defined
  • B. Roles must be combined to reduce the number of individuals needed on the project
  • C. During a procurement the senior supplier must be appointed from the customer organization
  • D. The project team must change at each end stage of the project life cycle

Answer: A

Explanation:
Section: Volume B


NEW QUESTION # 257
Which are purposes of the 'directing a project' process?
1. To enable the project board to be accountable for a project's success by making key decisions
2. To enable the project board to authorize work packages
3. To enable the project board to prepare the communication management approach
4. To enable the project board to exercise overall control of a project

  • A. 1 and 2
  • B. 3 and 4
  • C. 1 and 4
  • D. 2 and 3

Answer: C

Explanation:
The purposes of the 'directing a project' process are to enable the project board to be accountable for the project's success by making key decisions (1) and to exercise overall control of the project (4). This process ensures that strategic guidance and oversight are maintained, but does not directly involve the project board in authorizing work packages or preparing communication approaches-that's handled by the project manager.
References: = PRINCE27 Foundation handbook and online resources


NEW QUESTION # 258
Which is NOT confirmed during the Initiating a Project process?

  • A. How the method will be tailored for the size and complexity ofthe project
  • B. Who will make decisions on any changes during the project
  • C. How the management and specialist products of the project should be baselined
  • D. Whether the expected benefits have been achieved

Answer: D


NEW QUESTION # 259
Which is a feature of an effective project team?

  • A. It should plan and control effective communications with the project's stakeholders
  • B. It should rely on the team sitting together in order to easily build effective working relationships
  • C. It should consist of people with a wide range of skills, abilities and viewpoints
  • D. It should consist of full-time team members who can focus attention on the project's needs

Answer: C

Explanation:
An effective project team in PRINCE2 should be diverse, consisting of individuals with a variety of skills, abilities, and viewpoints. This diversity helps to ensure that the team can handle various aspects of the project effectively, bringing different perspectives to problem-solving and decision-making, which enhances the overall capability of the project team.References: (PRINCE2 7 Foundation Handbook, AXELOS)


NEW QUESTION # 260
Which is a purpose of the Directing a Project process?

  • A. Establish the level of control required by the Project Board after initiation
  • B. Provide the information required to confirm if it is worthwhile to initiate a project
  • C. Enable overall control of a project to be exercised by the Project Board
  • D. Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved

Answer: C


NEW QUESTION # 261
Which is one of the six aspects of project performance to be managed?

  • A. Efficiency
  • B. Estimate
  • C. Work
  • D. Timescales

Answer: D

Explanation:
Explanation
Reference
http://prince2.wiki/Introduction:_The_PRINCE2_Foundation_Training_Manual#Six_variables_.2F_six_perform


NEW QUESTION # 262
What theme estimates the cost of delivering the project?

  • A. Business Case
  • B. Progress
  • C. Change
  • D. Plans

Answer: D


NEW QUESTION # 263
Which risk response type is appropriate to respond to an opportunity?

  • A. Accept
  • B. Fallback
  • C. Transfer
  • D. Exploit

Answer: D

Explanation:
The risk response type "Exploit" is specifically designed to ensure that the opportunity is realized. This response is proactive and aims at making changes to exploit the opportunity fully, which aligns with managing opportunities within PRINCE2 risk management. References: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.


NEW QUESTION # 264
Which is a purpose of the 'controlling a stage' process?

  • A. To update a project plan to incorporate the actuals from a stage plan
  • B. To select and implement actions that will resolve deviations from a plan within tolerance
  • C. To obtain approvals for products delivered in a work package
  • D. To produce a team plan for the work to be assigned to a team manager

Answer: B

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Controlling_a_Stage#Purpose


NEW QUESTION # 265
Which is created during the Starting up a Project process?

  • A. Project management team role descriptions
  • B. Quality Register
  • C. Communication Management Strategy
  • D. Project mandate

Answer: A


NEW QUESTION # 266
How does the project plan help to support the 'manage by stages' principle?

  • A. By identifying the customer's quality expectations
  • B. By identifying the major control points and milestones
  • C. By defining products to ensure they are fit for purpose
  • D. By estimating the timescales and costs of the project

Answer: B

Explanation:
Reference http://prince2.wiki/Manage_by_stages


NEW QUESTION # 267
Which theme estimates the cost of delivering the project?

  • A. Plans
  • B. Business case
  • C. PROGEESS
  • D. Change

Answer: B

Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Business_Case


NEW QUESTION # 268
Which is a purpose of the Managing Product Delivery process?

  • A. Provide a controlled link between the Project Manager and the Team Manager(s)
  • B. Establish solid foundations for the project
  • C. Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
  • D. Enable the Project Board to request updates to the current Team Plan

Answer: A

Explanation:
Section: Volume A


NEW QUESTION # 269
Which are characteristics of stakeholders?
1. They are often affected by the project
2. They agree with every project objective
3. They are only/always external to the corporate organization
4. They typically interact with the project

  • A. 1 and 2
  • B. 3 and 4
  • C. 1 and 4
  • D. 2 and 3

Answer: C

Explanation:
Stakeholders in PRINCE2 are typically characterized by being affected by the project (either through impact or interest) and frequently interacting with the project, contributing inputs or being consulted for various aspects. This recognizes stakeholders as both internal and external to the organization, and not all stakeholders necessarily agree with every project objective. References: PRINCE2 Foundation Handbook, Stakeholder section.


NEW QUESTION # 270
Which is a purpose of the 'Starting up a Project' process?

  • A. To define the means of communication between the project and corporate or programme management
  • B. To define the project controls
  • C. To record any identified risks in the Risk Register
  • D. To provide information so a decision can be made as to whether a project is viable and worthwhile to initiate

Answer: D

Explanation:
Section: Volume B


NEW QUESTION # 271
......


EXIN PR2F is a certification exam that tests the knowledge of the PRINCE2 methodology at the foundation level. PRINCE2 stands for Projects IN Controlled Environments and is a widely used project management framework. EXIN PR2F is a written exam that assesses a candidate's understanding of PRINCE2 principles, processes, themes, and techniques.

 