NEW QUESTION 11
What tool is used to synchronize changes between SAP ERP and SAP S/4HANA maintenance tracks?\
- A. Retrofit
- B. SAP code vulnerability analyser
- C. Business process change analyser
- D. SAP code inspector
Answer: A
NEW QUESTION 12
Which activities are part of the Design and Configuration application of the SAP Activate methodology?
There are 2 correct answers to this question.
Response:
- A. Schedule kick-off workshop
- B. Conduct Scope Validation
- C. Confirm Integration prerequisites
- D. Perform Fit/Gap Analysis
Answer: B,D
NEW QUESTION 13
What is SAP Activate?
Please choose the correct answer.
Response:
- A. A step-by-step instruction on how to remove from SAP best practices to your custom solution
- B. A bundle of ASAP , SAP Launch , and Rapid Deployment Solutions
- C. A methodology for each of the deployment modes (cloud , on-premise, hybrid)
- D. A combination of SAP best practices , methodology, and guided configuration
Answer: D
NEW QUESTION 14
Which tools does SAP Activate provide to support Guided Configuration?
There are 3 correct answers to this question.
Response:
- A. Expert Configuration
- B. Solution Builder
- C. SAP Solution Composer
- D. Model Company
- E. Self Service Configuration
Answer: A,B,E
NEW QUESTION 15
What tool provides sizing estimators for the "system conversion" transition path?
- A. SAP best practices explorer
- B. SAP Transformation navigator
- C. Scope and effort analyser
- D. SAP readiness check
Answer: D
NEW QUESTION 16
In the "new implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape? There are 2 correct answers to this question.
- A. DQAS
- B. Starter system
- C. P-system
- D. DEV
Answer: A,D
NEW QUESTION 17
Which artifacts in the Testing work stream are created within the Realize phase for the New Implementation of SAP S/4HANA Cloud" transition path?
There are 2 correct answers to this question.
Response:
- A. Reporting Functional Specifications
- B. User Acceptance Test - Plan
- C. Functional Specifications
- D. Functional Test Scenarios
Answer: B,D
NEW QUESTION 18
Which of the following are not phases of the SAP Activate methodology?
There are 2 correct answers to this question.
Response:
- A. Go-Live & Support
- B. Preparation
- C. Prepare
- D. Realize
Answer: A,B
NEW QUESTION 19
Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning?
Please choose the correct answer.
Response:
- A. Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity
- B. Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks
- C. Product Owner's relative estimate of the effort that will be needed to implement the user story
- D. Relative estimate in ideal person days that reflects the best estimate provided by the project team
Answer: D
NEW QUESTION 20
Which statement are part of the 5 golden rules for SAP S/4HANA Cloud single tenant edition?
There are 2 correct answers to this question.
- A. Foster cloud mindset and adherence to the fit to standard approach
- B. Document deviations from golden rules for transparency and future use in upgrade
- C. Use SAP solution manager 7.2 with focused build
- D. Stick to the security standard of the customer organisation
Answer: A,B
NEW QUESTION 21
What sprint types are part of the SAP activate methodology There are 3 correct answers to this question.
- A. Initial
- B. Firm-up
- C. Daily
- D. Build
- E. Foundational
Answer: B,D,E
NEW QUESTION 22
What are the responsibilities of the Project Team on level 4 in the picture below?
There are 2 correct answers to this question.
Response:
- A. Identify and resolve issues and risks
- B. Set Project policy, standards and oversight
- C. Perform status reporting and communication
- D. Set business priorities, goals and objectives
Answer: A,C
NEW QUESTION 23
Where can you find the integration content? There are 3 correct answers
- A. SAP API business hub
- B. Cloud integration automatic service
- C. SAP Solution manger
- D. SAP cloud appliance library
- E. SAP Best practices explorer
Answer: A,D,E
NEW QUESTION 24
Why is there NO Sandbox system in the "New Implementation of SAP S/4HANA Cloud, Single Tenant Edition" transition path?
Please choose the correct answer.
Response:
- A. Because the customer may use the SAP Model Company
- B. Because the project team uses the DEV system to confirm solution fit and define delta requirements
- C. Because the Fit-to-Standard workshop is conducted using the Q-system
- D. Because SAP S/4HANA Cloud, Single Tenant Edition, contains predefined business processes which should NOT be changed
Answer: A
NEW QUESTION 25
What is the term used for workshops, which are intended to set value targets, validate SAP Standard functionality against customer requirements.
And collect delta requirements in the "New Implementation of SAP S/4HANA" transition path?
Please choose the correct answer.
Response:
- A. Fit-to-Standard
- B. Design Thinking
- C. Solution Validation
- D. Delta Design
Answer: C
NEW QUESTION 26
Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase?
There are 3 correct answers to this question.
Response:
- A. Solution Scope and Value Determination
- B. Design for the Gaps and Deltas
- C. Baseline Build
- D. Validation Workshops
- E. Data Migration Approach
Answer: B,D,E
NEW QUESTION 27
How many deliverables are a part of the Key Deliverable 'Project Initiation'?
Please choose the correct answer.
Response:
- A. Three
- B. One
- C. Two
- D. Four
Answer: D
NEW QUESTION 28
Which of the following belong to the Application Design and Configuration work stream for SAP S/4HANA Cloud in the Explore phase?
There are 2 correct answers to this question.
Response:
- A. Fit-to-standard workshop
- B. Integration prerequisites confirmation
- C. Configuration definition
- D. Kick-off workshop
Answer: A,C
NEW QUESTION 29
Which new role is introduced in the SAP activate methodology in a full scrum team?
- A. Product owner
- B. System administrator
- C. Project manager
- D. Application consultant
Answer: D
NEW QUESTION 30
How often will an upgrade be performed on an SAP S/4HANA cloud single tenant edition environment?
- A. Every year
- B. Schedule is defined by service level agreement for SAP HANA enterprise cloud and SAP S/4HANA Cloud single tenant edition services.
- C. One upgrade and two feature packs per year
- D. Every quarter
Answer: B
NEW QUESTION 31
According to the definition of done, which activity must be completed for each sprint?
- A. End-user training must be delivered
- B. The solution must be built and configured in the development system (DEV)
- C. Functionality must be tested in the quality system (QAS)
- D. Functionality must be released to the business
Answer: B
NEW QUESTION 32
What is the key characteristics of the agile project approach
- A. Formal and detailed documentation
- B. Frequent Quality Gates
- C. Iterative build with frequent inspections
- D. Frequent and detailed project scheduling
Answer: C
NEW QUESTION 33
What is the purpose of a firm-up sprint?
- A. To revise the release plan and sprint plan
- B. To perform string test
- C. To demonstrate functionality from previous sprints
- D. To run an end-to-end integration test
Answer: B
NEW QUESTION 34
Which key deliverable includes the development of RICEFW objects?
Please choose the correct answer.
Response:
- A. Sprint Execution
- B. Development Build
- C. Custom Extensions Management
- D. Enhancement Delivery
Answer: D
NEW QUESTION 35
......