An architect is rehabilitating a historic federal landmark that requires repairs to a garden wall. The existing brick appears to be in good condition; the mortar shows significant signs of deterioration.
Which strategy should the architect propose to repair the damaged wall?
Correct Answer: C Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).


An architect is designing a school building that features a flat roof with a low parapet wall in a wet climate region. The client wants to minimize maintenance requirements and focus on keeping water from the walls.
What parapet coping detail would be most appropriate for the architect to select for this project?
Correct Answer: A Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
In an air-conditioned space in a tropical environment, roof insulation is being applied above a structural deck.
In order to avoid problems related to condensation, where should the vapor barrier be installed?
Correct Answer: A Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
During plan review of an office building, the reviewer informs the architect of new regulations that require storage rooms greater than 150 sf be 1-hour fire rated. The proposed design has three 200 sf storage rooms that must meet the fire protection requirements. The architect needs to recommend how to meet this requirement with minimal effect on cost, time, and program.
Correct Answer: C Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
In a brick veneer wall, what is the primary purpose of the 2-inch air space between the back of the brick and the sheathing?
Correct Answer: D Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
During the documentation of an office building, the owner requests a fitness center amenity be added to the scope. The mechanical engineer informs the architect that the mechanical unit currently located on a utility mezzanine will need to increase in size to accommodate the required increased capacity.
Who should the architect confirm with that the larger unit will work in this location?
Correct Answer: D Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).

Refer to the exhibit.
An architect is working on an airport lounge project. The 9,000 SF floor plan includes an open, double-height space. Due to area limitations, all program requirements cannot fit within the 9,000 SF floor plan. A mezzanine level with one exit is being proposed to solve this programming constraint. There are adequate exits available on the main floor plan to pick up the additional occupant load from the mezzanine.
Which method of mezzanine construction should the architect design?
Correct Answer: C Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).

Refer to the exhibit.
For which of the following connections could diagonal bracing be eliminated?
Correct Answer: C Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
Specifications and details for repointing deteriorated masonry joints in historic soft-brick buildings should result in which one of the following?
Correct Answer: B Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).