Scenario: Rollins Manufacturing
Please read this scenario prior to answering the question
Rollins Manufacturing is a major supplier in the automotive industry, headquartered in Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own Manufacturing Requirements Planning (MRPII) system, production scheduling, and custom developed applications that drive the automated production equipment at each plant.
Rollins is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current MRPII and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems.
It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Rollins Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their MRPII and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Rollins Manufacturing Scenario
You are serving as the Lead Enterprise Architect for the Common ERP Deployment architecture project.
One of the earliest initiatives in the Enterprise Architecture program at Rollins was the definition of a set of IT principles and architecture principles that are well aligned with the overall enterprise principles. These now need to be updated to address the concerns raised.
You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution.
[Note: You should assume that Rollins has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.] Based on TOGAF 9, which of the following is the best answer?
Correct Answer: C Vote an answer
Magic Wand Corporation manufactures a range of equipment used by magician worldwide. The global popularity of a series of children's books describing the formative years of a budding wizard and his various escapades at wizard school has driven unprecedented sales growth in the magical equipment market.
The current IT systems at Magic Wand are struggling to cope with the high volumes in this growth market.
The CIO wants to persuade the board of Magic Wand Corporation to make a greater investment in the IT systems to cope with the new higher transaction volumes. On of the key components the CIOs wants to include when he approaches the board is a description of the current problems and how they may be addressed from an architectural point of view.
As the High Architect of Magic Wand Corporation, the CIO has delegated the task of creating a vision for the future Architecture to you.
Which of the following answers best describes how TOGAF recommends delivering an Architecture Vision for the CIO?
Correct Answer: A Vote an answer
TP Banking is a strong financial institute with a well-known acquisition history with an internal IT department managing over 100 projects related to infrastructure and services.
The CIO has decided to create an Enterprise Architecture based on TOGAF 9 as reaction to the difficult market conditions. An Architecture Vision and a set of domain architectures were approved. The CIO is asking you (the Lead Architect) to define an Implementation and Migration Plan that realizes the vision already agreed with the stakeholders involved.
Refer to the scenario above
You are leading a group of domain architects and you are working with the corporate PMO, the business strategy team and service operations. You are meeting the stakeholders to clarify how you want to proceed with the Implementation and Migration Plan.
Choose one of the following answers
Correct Answer: B Vote an answer
Scenario: Glacier Ridge LLC
Please read this scenario prior to answering the question
Glacier Ridge LLC is a vacation property management firm that is growing through acquisition. It manages over 200 resort properties across North America. Many of the resort properties use the same internal IT systems that they used before they were acquired. Until recently, the only requirement that has been placed en each property is that they use a standard financial reporting system to report their financials ID the headquarters on a weekly basis. The CEO has stated his concerns about the inefficiencies of the current approach and identified the need to change. He has defined a new strategic vision that will enhance the Glacier Ridge property business by standardizing its operations across the network to provide consolidated financial, human resources, logistics, sales and marketing, and yield management. He has also stated that he expects results by the end of the current fiscal year. These changes will provide the company with improved utilization of its capacity and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising into key markets to improve yields. Glacier Ridge has mature enterprise architecture (EA) practice and uses TOGAF 9 as the method and guiding framework.
The CIO is the sponsor of the activity. In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire firm, including detailed requirements and recommendations.
Based on the recommendations from the initial engagement, Glacier Ridge has embraced an Architecture Vision to adopt an enterprise application that is tailored to the needs of the hospitality industry.
Refer to the Glacier Ridge scenario
Your role is that of Chief Architect. You have been asked to recommend the best approach to take in this architecture engagement to realize the CEO's vision. Based on TOGAF 9, which of the following is the best answer?
Correct Answer: C Vote an answer
Your role is that of a consultant to the Lead Enterprise Architect in a company that develops wind turbines for use in wind farms. The company has three manufacturing facilities, one in North America, one in Asia, and one in Europe. Each of these facilities supplies the power industry in its region.
The company recognizes that the long-term technical potential of wind energy can address the current global dependency on carbon fuels, in order to do so this will require wind turbines to be installed over the large areas and in areas of higher wind resources. In particular offshore wind farms can contribute substantially more energy than land stationed turbines.
The research arm of the company has pioneered the development of an offshore wind turbine design, with an improved turbine blade and power system, that will produce up to 20% more energy. This will allow the production of significantly more salable energy. This new design is ready to go into production.
The company has a mature Enterprise Architecture practice supported by a cross-functional Architecture Board and uses the TOGAF standard. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
As part of putting the new design into production, a pilot architecture project has defined an updated standard approach for controlling the automated test systems used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new automated test system controller for each location. The Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and a low blade failure rate.
You have been asked to recommend the best approach to address the Chief Engineer's concern.
Based on the TOGAF Standard, Version 9.2, which of the following is the best answer?
Correct Answer: D Vote an answer
MightyGears produces components for the Car industry. Driven by the global financial downturn they are looking to reduce IT costs. They believe there is a cost saving opportunity within IT but this is not quantified in terms of potential savings nor is there an agreed target architecture. Final decisions on the solutions are not yet fully agreed. They have completed the first pass architecture and now are looking at the best opportunities and solutions to meet their financial goals.
You are the Chief Architect from a consulting organization brought into review the work to date by MightyGears and to make recommendations to the CIO and the board on the opportunities and solutions present.
Refer to the scenario above
Which of the following answers best describes how TOGAF recommends examining the opportunities and solutions before presenting to the board?
Choose one of the following answers
Correct Answer: D Vote an answer
You are working as a consultant to the Chief Architect at an intelligent and security organization responsible for securing government communications and information systems. These provide real-time, highly secure communication of voice, video, and message data to remove locations around the world. The agency has recently received information from intelligence sources that the current encryption protocols may no longer be secure. In response, a program is underway to upgrade the systems.
The agency has an established Enterprise Architecture (EA) capability based on the TOGAF standard. The Executive Director of the agency is the sponsor of the EA capability.
Since reliable, high-preformcane, and secure communications are essential to be preserving national security, the Executive Director has placed stringent requirements for the architecture of the upgraded systems. It must be able to provide assurance of the upgraded systems. It must be able to provide assurance and verification of specific performance measures on the key services that are most crucial for system operation. Focusing on these service-level details and specific measurements will allow stricter requirements to be enforced in service contracts. It will also provide a high degree of assurance that necessary performance is being delivered and that notifications will occur if any critical service fails to perform as required.
A portion of the program budget has been allocated to conduct a review of the EA. The scope of the review is to evaluate the processes, content, and governance of the EA capability to ensure that the higher target performance and service levels required by the upgraded system can be achieved.
The Chief Architect has noted that the core EA artifacts that have been in use are not able to describe these new capabilities. The artifacts do not have explicit provisions for defining the in-depth measurement requirements regarding specific services required for the system. She has learned that certain services within the current system have service measurement implemenations that match some of the new requirements, but they are only used in a few areas.
Recent EA efforts at another national agency have produced generalized high-performance communication system models to realize similar requirements in a critical defense system involving secure communications. It is possible that these models may be useful for the upgrade program.
[Note: You may need to refer to the Content Metamodel chapter, section 30.4 (located in Part IV) of the reference text in order to answer this question.] You have been asked to make recommendations for tailoring the Architecture Content Metamodel to accommodate the requirements of the upgraded system.
Based on the TOGAF Standard, Version 9.2, which of the following is the best answer?
Correct Answer: C Vote an answer
You are serving as an Enterprise Architect at a large aerospace company. It designs, manufactures and sells civil and military aviation products worldwide and manufactures in multiple countries both inside and outside of the European Union. The company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems.
Recently, several procurement processes, within the civil aviation business, have had problems related to the timing of purchases, which has led to excess inventory. The Vice President in change of Supply Chain Management has made the decision to consolidate and reduce redundant procurement processes and systems.
He has committed to the CEO that the business will move to a "Just-in-time" procurement system so as to keep inventory costs low.
The TOGAF standard is used for internal Enterprise Architecture activities. At presents, there are no architectural assets in the Architecture Repository related to this initiative. All assets will need to be acquired, customized, or created from scratch. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving the existing procurement processes or systems.
This project is using an iterative approach for executing the Architecture Development Method (ADM). The architecture development project has completed the Architecure Vision Phase and has started a number of iteration cycles to develop the Architecture. As a packeged application is being considered, the next iteration will include both the Business and Application Architectures.
Stakeholder concerns that should be addressed by these architectures include:
1. What groups of people should be involved in procurement-related business processes?
2. What applications will these groups use once the architecture development is complete?
3. What non-procurement applications will need to be integrated with the new procurement applications?
4. What are the dependencies between the non-procurement and the new procurement applications?
[Note: You may need to refer to the Architectural Artifacts chapter, section 31.6 (located in Part IV) within the reference text in order to answer this question.] You have been asked to identify the most appropriate catalogs, matrices, and diagrams to support the next iteration of Architecture development.
Based on the TOGAF Standard, Version 9.2, which of the following is the best answer?
Correct Answer: D Vote an answer