Showitoff is an organisation specialising in the design and production of wall decorating materials for the domestic market. During an ISO 14001 certification audit of the site, the auditor comes across an open, walled area just outside the maintenance department. It contains various scraps of wood and metal as well as several rusty components. They are lying on an oily floor. When asked about it, the EMS Manager states that he presumes that the materials come from maintenance work.
The auditor interviews the Maintenance Manager in his department. He notes that shelves containing various spares are well labelled and neatly stacked. He asked about the " dump " outside and is told that it contains some excess materials that the Manager likes to keep in case they come in handy at some stage. The auditor points out that the " dump " might be classed under regulations as a landfill site, which requires an operating licence. The Maintenance Manager is not aware of such a licence.
The auditor decides to review the process for evaluation of compliance with environmental regulations in more depth.
Select three options that provide a meaningful audit trail for this process.
The auditor interviews the Maintenance Manager in his department. He notes that shelves containing various spares are well labelled and neatly stacked. He asked about the " dump " outside and is told that it contains some excess materials that the Manager likes to keep in case they come in handy at some stage. The auditor points out that the " dump " might be classed under regulations as a landfill site, which requires an operating licence. The Maintenance Manager is not aware of such a licence.
The auditor decides to review the process for evaluation of compliance with environmental regulations in more depth.
Select three options that provide a meaningful audit trail for this process.
Correct Answer: A,B,H
Vote an answer
An audit team leader arrives at a steel fabrication organisation that manufactures fire escape stairs to carry out a Stage 2 certification audit. At a meeting with the EMS Manager, she is informed that they have secured their largest contract from a construction organisation to manufacture and install fire escape stairs. They appointed a subcontractor to perform the installation work. The EMS Manager wants the ISO 14001 audit extended to cover the installation site.
During the audit, a team member found that several complaints had been made to the organisation regarding their installation operators being seen to dispose of excess paint into the site drains, which breached legal requirements. The EMS Manager blames the contractors they had to take on because of the big contract. The auditor raises a nonconformance against clause 8.1 of ISO 14001.
Which one of the following statements would support this finding?
During the audit, a team member found that several complaints had been made to the organisation regarding their installation operators being seen to dispose of excess paint into the site drains, which breached legal requirements. The EMS Manager blames the contractors they had to take on because of the big contract. The auditor raises a nonconformance against clause 8.1 of ISO 14001.
Which one of the following statements would support this finding?
Correct Answer: B
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
A key audit process is the way auditors gather information and determine the findings ' characteristics. Put the actions in the correct order to complete this process.


Correct Answer:

Explanation:
A screenshot of a computer AI-generated content may be incorrect.

This sequence is derived from ISO 19011:2018 - Guidelines for Auditing Management Systems, which is used in conjunction with ISO 14001:2015 by auditors. Specifically, the audit process steps during the " conducting the audit " phase include:
Determining the source of information (Clause 6.4.5): Includes documents, interviews, records, and observations.
Collecting data by sampling (Clause 6.4.6): Sampling helps in managing resources and gathering relevant evidence effectively.
Gathering audit evidence (Clause 3.8): Audit evidence is the data collected and verified to support findings.
Evaluating against audit criteria (Clause 3.9): Evidence must be evaluated against standards such as ISO
14001 requirements, internal policies, etc.
Developing audit findings (Clause 6.4.9): Conclusions regarding conformance, nonconformance, and opportunities for improvement.
Review of findings (Clause 6.4.10): Cross-verification and validation before finalizing results.
Audit conclusions (Clause 6.4.11): Final statements summarizing the audit based on findings.
This structured process ensures audits are performed impartially, with verifiable, evidence-based outcomes that contribute to continual improvement.
Reference:
ISO 19011:2018, Clauses 6.4.5 to 6.4.11
ISO 14001:2015, Clause 9.2 - Internal audit requirements
A small services organisation has been contracted to handle the disposal of waste for a local hospital. You are an auditor conducting a Stage 2 audit of the care home to ISO 14001. You are reviewing the contract with the Service Manager (SM). An addendum to the contract only requires that biological waste is disposed of in the most environmentally friendly way, without reference to any regulatory requirements.
You: How was the waste disposal plan for the contract developed?
SM: We have a basic template that covers the materials, labour requirements and methods to be employed.
Some of that is specified by the contractor.
You: How does the plan deal with specific items like biological waste, which are included in the contract and can pose biological hazards to the environment?
SM: The basic plan covers general waste, but we have an addendum that covers biological waste.
You: Are you aware of the regulatory requirements for waste disposal standards in hospitals?
SM: Yes but we depend on the contractor to look after that side of things.
You raise a nonconformity against section 8.1.d of ISO 14001.
At the Stage 2 closing meeting of the audit, the EMS Manager objects to the nonconformity raised and asks for it to be withdrawn. He insists that they meet all the regulations.
Choose one of the options that the audit team leader should take in response to the request.
You: How was the waste disposal plan for the contract developed?
SM: We have a basic template that covers the materials, labour requirements and methods to be employed.
Some of that is specified by the contractor.
You: How does the plan deal with specific items like biological waste, which are included in the contract and can pose biological hazards to the environment?
SM: The basic plan covers general waste, but we have an addendum that covers biological waste.
You: Are you aware of the regulatory requirements for waste disposal standards in hospitals?
SM: Yes but we depend on the contractor to look after that side of things.
You raise a nonconformity against section 8.1.d of ISO 14001.
At the Stage 2 closing meeting of the audit, the EMS Manager objects to the nonconformity raised and asks for it to be withdrawn. He insists that they meet all the regulations.
Choose one of the options that the audit team leader should take in response to the request.
Correct Answer: C
Vote an answer
During a Stage 1 audit, the EMS Manager asks that the audit includes coverage of a new storage site on the other side of town that they have taken over since the application was made.
Which two of the following actions should the auditor take?
Which two of the following actions should the auditor take?
Correct Answer: A,D
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
An internal auditor of a manufacturer of aluminium products for the car industry asked to see the most recent management review minutes and found no reference to the completion of some of the current environmental objectives. He raised a nonconformity against section 9.3.c of ISO 14001 in Report IA202. The nonconformity (NC3) stated:
" Top management has not analysed why some of the environmental objectives have been met since the last management review. " When discussing the finding with the Environmental Manager, the auditor was informed that planned actions taken to complete the current environmental objectives were specifically covered in the internal audit programme and did not need any further work done.
Select one of the options which would constitute an effective response by the Environmental Manager to the nonconformity.
" Top management has not analysed why some of the environmental objectives have been met since the last management review. " When discussing the finding with the Environmental Manager, the auditor was informed that planned actions taken to complete the current environmental objectives were specifically covered in the internal audit programme and did not need any further work done.
Select one of the options which would constitute an effective response by the Environmental Manager to the nonconformity.
Correct Answer: D
Vote an answer
An audit team leader arrives at a steel fabrication organisation that manufactures fire escape stairs to carry out a Stage 2 certification audit. At a meeting with the EMS Manager, she is told that they have won their biggest contract from a construction organisation to manufacture and install fire escape stairs. They appointed a subcontractor to perform the installation work. The EMS Manager wants the ISO 14001 audit extended to cover the installation site.
Select which one of the options is the correct response by the auditor.
Select which one of the options is the correct response by the auditor.
Correct Answer: C
Vote an answer