A user story was estimated at five ideal hours. On a normal eight hour working day, the team gets about four hours of actual work time.
What would be the elapsed time required to complete the Story?
Correct Answer: A Vote an answer
A team is estimating story points. They estimate that the story falls between a large (13) and a medium (5) and they assign a story point of 8.
What is this technique called?
Correct Answer: B Vote an answer
A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint.
Who may best prepare this report?
Correct Answer: A Vote an answer
What message can you give to a customer about a key benefit of using Scrum?
Correct Answer: B Vote an answer
A team selects a Product Backlog Item (PBI) for the Sprint Backlog. What must a team do to finish the Product Backlog Item it selects?
Correct Answer: B Vote an answer
An engineering organization is transforming their project management method to use Agile Scrum.
What is the best approach to the transformation?
Correct Answer: C Vote an answer