SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 - C_TPLM22_67 Exam Practice Test
In requirements grouping which indicator must be set for WBS elements that determines whether the requirements may be grouped into one WBS element and how?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Vote an answer
Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,E
Vote an answer
Which of the following cannot be entered when using service activities in networks for planned and unplanned services?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Vote an answer
Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element.
Which of the following costs can be planned?
There are 3 correct answers to this question.
Response:
Which of the following costs can be planned?
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,D
Vote an answer
Which of the following cost planning transactions are related to Account assignment?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: B,C,D
Vote an answer
What is the starting point for milestone billing?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Vote an answer
When you create service activity in your network, what data can be entered? (3)
Correct Answer: A,B,C
Vote an answer
Which type of order is created at BOM level to cover requirements when a material shortage occurs in material planning?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Vote an answer
What do you use in the parameters for network type to specify whether a workflow is to be generated in the case of purchase order relevant change?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Vote an answer
Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Vote an answer
Your customer uses Progress Tracking for network components and maintains dates of events manually. They need to implement scheduling of events. What is the prerequisite for scheduling of events? *
Correct Answer: D
Vote an answer
Which type of network does not allow you to assign materials directly, but only indirectly using a bill of materials?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Vote an answer
Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,D
Vote an answer