An Agile team uses a burndown chart and a task board to track progress within each iteration. In the burndown chart, the x-axis represents the days of iteration, while the y-axis represents the story points.
The task board uses columns: "To Do", "Ongoing", "Done".
A user story for the current iteration has 20 story points and 4 tasks (T1, T2, T3, T4). At the end of Day 5, all are in "Ongoing". At the end of Day 6, T1 and T2 move to "Done", while T3 and T4 remain "Ongoing".
Which of the following statements would you expect most likely to be true at the end of Day 6?
The task board uses columns: "To Do", "Ongoing", "Done".
A user story for the current iteration has 20 story points and 4 tasks (T1, T2, T3, T4). At the end of Day 5, all are in "Ongoing". At the end of Day 6, T1 and T2 move to "Done", while T3 and T4 remain "Ongoing".
Which of the following statements would you expect most likely to be true at the end of Day 6?
Correct Answer: B
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
Which of the following statements is FALSE regarding early and frequent feedback?
Correct Answer: B
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
Which of the following is the BEST way for a test team to keep its independence when working in an Agile development environment?
Correct Answer: D
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
Which of the following statements about Agile retrospectives is true?
Correct Answer: A
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
An Agile team is working on a project to develop an image editing tool. In the current version, the
'Settings' GUI allows users to adjust exposure, contrast, and saturation. A session-based exploratory testing session is planned to find issues with parameter combinations that cause undesired image effects.
Which of the following would you expect to be the best charter to support this exploratory testing session?
'Settings' GUI allows users to adjust exposure, contrast, and saturation. A session-based exploratory testing session is planned to find issues with parameter combinations that cause undesired image effects.
Which of the following would you expect to be the best charter to support this exploratory testing session?
Correct Answer: D
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
Which of the following would provide the MOST independence for testers working with agile teams?
Correct Answer: C
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
Which of the following statements about the testing quadrants model is true?
Correct Answer: D
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
Which of the following statements would you expect to be the MOST direct advantage of the whole-team approach?
Correct Answer: B
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
A calculator application is being developed. The third sprint has been planned to add functionality to the calculator to allow scientific calculations.
Which TWO examples below represent activities that would likely be managed on an agile task board for the third sprint?
1) A task to design the features planned for the next sprint.
2) A task to run an acceptance test for a user story.
3) A task to automate regression tests.
4) A task to participate in training in preparation for the fourth sprint.
5) A task to produce a daily progress report for the agile team members.
Which TWO examples below represent activities that would likely be managed on an agile task board for the third sprint?
1) A task to design the features planned for the next sprint.
2) A task to run an acceptance test for a user story.
3) A task to automate regression tests.
4) A task to participate in training in preparation for the fourth sprint.
5) A task to produce a daily progress report for the agile team members.
Correct Answer: C
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).