ISTQB Certified Tester Foundation Level 2018 - CTFL-2018 Exam Practice Test
When comparing Static and Dynamic test techniques, which of the following statements is TRUE?
Correct Answer: B
Vote an answer
You are performing a review of your colleague's test cases based on the following test basis document:

The Test Cases are as follows:
TC1. Success - valid 'User Name' and 'Password'; Customer Menu displayed TC2. Failure - 'User Name' field has blank entry; Error Number 12 displayed TC3. Failure - 'User Id' entered does not exist on database (i.e. unregistered user); Error Number 23 displayed TC4. Failure - 'Password' entered does not match user's password on database; Error Number 24 displayed You are guided by the following checklist in your review:
C1. There must be one test case to cover success
C2. There must be one test case for each error path (e.g. validation failure) C3. Each test case must use terminology consistent with the test basis document (field names, error numbering, etc.) Record a separate defect for each missing test case (checklist items C1 and C2) and for each test case that does not meet checklist item C3.
How many defects should you record?

The Test Cases are as follows:
TC1. Success - valid 'User Name' and 'Password'; Customer Menu displayed TC2. Failure - 'User Name' field has blank entry; Error Number 12 displayed TC3. Failure - 'User Id' entered does not exist on database (i.e. unregistered user); Error Number 23 displayed TC4. Failure - 'Password' entered does not match user's password on database; Error Number 24 displayed You are guided by the following checklist in your review:
C1. There must be one test case to cover success
C2. There must be one test case for each error path (e.g. validation failure) C3. Each test case must use terminology consistent with the test basis document (field names, error numbering, etc.) Record a separate defect for each missing test case (checklist items C1 and C2) and for each test case that does not meet checklist item C3.
How many defects should you record?
Correct Answer: B
Vote an answer
Your agile project has scheduled a final sprint before release to fix and re-test all open defects with a priority level of 3 or above.
The following defect report shows the defect fields that are currently being captured on the system.
Title: Unable to add excursions to pre-paid cruises
Date raised: 21/05/18
Author: Emma Rigby
Status: Fixed
What occurred: I went to book an excursion for a pre-paid cruise but received an error message saying,
'Facility not available'. I can book excursions on cruises that have not yet been fully paid.
What should have occurred: Requirement 3.12 says clearly that customers can add excursions after cruises have been fully paid so the facility should have been available (when an additional amount may now need to be paid).
Priority: 2
Software build: 2.1
Test level: System test
Environment details: System test 3
Which of ONE of the following additional defect report fields would be MOST beneficial for the sprint team to add?
The following defect report shows the defect fields that are currently being captured on the system.
Title: Unable to add excursions to pre-paid cruises
Date raised: 21/05/18
Author: Emma Rigby
Status: Fixed
What occurred: I went to book an excursion for a pre-paid cruise but received an error message saying,
'Facility not available'. I can book excursions on cruises that have not yet been fully paid.
What should have occurred: Requirement 3.12 says clearly that customers can add excursions after cruises have been fully paid so the facility should have been available (when an additional amount may now need to be paid).
Priority: 2
Software build: 2.1
Test level: System test
Environment details: System test 3
Which of ONE of the following additional defect report fields would be MOST beneficial for the sprint team to add?
Correct Answer: D
Vote an answer