In a chilled water thermal energy storage system, chilled water is stored at 4°C and used for supply water.
Chilled water return is 14°C. Calculate the storage capacity required to hold 50 GJ of thermal cooling. (The specific heat of water (C) is 4.2 kJ/kg-°C. Assume no system losses.)
Correct Answer: B Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
Which type of lighting control technique operates in "manual on" and "auto-off mode, and can be used in situations where there is brief occupancy that do not need lights on?
Correct Answer: A Vote an answer
You are using a performance contract to finance the added cost of using more-efficient equipment in the construction of a new building. Which of the following International Performance Measurement and Verification Protocol (IPMVP) options would you use to verify annual energy savings?
Correct Answer: E Vote an answer
How does an enthalpy-based economizer control operate?
Correct Answer: C Vote an answer
The set point for the chiller supply water temperature is varied as a function of the thermal demand for space cooling. What do you call this control strategy?
Correct Answer: D Vote an answer
Using an interest rate of 15%, an energy project has a net-present value (NPV) of $3,500. Which statement is true about the project's internal rate of return (IRR)?
Correct Answer: B Vote an answer
The primary advantage of predictive maintenance over preventive maintenance in building energy systems, is that predictive maintenance:
SELECT THE CORRECT ANSWER
Correct Answer: C Vote an answer
Which motor parameter is the most difficult to measure with precision?
Correct Answer: E Vote an answer
A controller has a signal output that can range from 4 to 20 mA (milli-amperes). The controller regulates the output temperature from a three-way mixing valve from 5°C to 15°C. What is the control gain?
Correct Answer: E Vote an answer