SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 - C-TSCM42-67 Exam Practice Test

Which of the following elements can be used in a process order? (Choose three)
Correct Answer: A,C,D Vote an answer
Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order.
Which BOM item category must you set to fulfill this requirement?
Correct Answer: B Vote an answer
From what point can you no longer use the Read PP master data in the production order?
Correct Answer: A Vote an answer
Which function is supported by production orders?
Correct Answer: B Vote an answer
You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you want to use a second sequence on other work centers for operations 30 and 40.
Which sequence category do you use to create the second sequence in the system?
Correct Answer: C Vote an answer
You want to reduce the uncertainty caused by fluctuating requirements for a finished product by using a dynamic safety stock in SAP ECC.
On which specifications is the dynamic safety stock calculation based?
Correct Answer: D Vote an answer
Which of the following items of master data are needed for repetitive manufacturing? (Choose three)
Correct Answer: A,C,E Vote an answer
What do you have to consider regarding consumption? (Choose two)
Correct Answer: C,D Vote an answer
In which master data object do you set the standard values for an operation?
Correct Answer: B Vote an answer
In the SAP ECC system, a material is produced using production orders. The planning table for repetitive manufacturing should be used to plan line loading for this material. On the initial screen of the planning table, you select this material and then receive a message informing you that you cannot use the planning table for this material (see attached screenshot).

What could be the reason?
Correct Answer: D Vote an answer