SAP Certified Application Associate - SAP S/4HANA Project Systems - C-TS412-1909 Exam Practice Test

Revenues & Payment
A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal ..
correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?
Correct Answer: A Vote an answer
Cost & budget
A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget.
What action do you have tsolve the problem?
Correct Answer: D Vote an answer
Your customer has created networks with internal activities and generated capacity requirements. Now,
they want to analyze the capacity requirements of their project. Which report do you recommend?
Correct Answer: D Vote an answer
Which of the following statements apply to project versions? Note: There are 2 correct answers to this question
Correct Answer: A,D Vote an answer
Which statement is valid regarding networks?
Correct Answer: D Vote an answer
Cost and budget
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce..
Which setup do you recommend?
Correct Answer: D Vote an answer
Dates
How are earliest dates and latest dates of activities schedule?
Correct Answer: B Vote an answer
A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question
Correct Answer: A,D Vote an answer