SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 - C-TPLM22-67 Exam Practice Test
How can you distinguish between service activities and external activities while accessing the detailed information for service activities on the external tab page?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,C
Vote an answer
What are the pre-requisites for distributing work to HR Resources?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,B
Vote an answer
How do you create a detailed payment schedule if the expense for an external activity or purchased component is not paid with a single invoice?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Vote an answer
Which account assignment category is important for non-valuated project stock with WBS and sales order item?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Vote an answer
Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,D
Vote an answer
Which manual cost planning method is used in WBS?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: B,C,D
Vote an answer
Which of the following can be derived automatically when you carry out scheduling in projects with networks?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: B,C
Vote an answer
You are using the billing and down payment processing in Sales and Distribution and updating the actual data to billing elements in the project system.
Which of the following business processes can be mapped in Sales and Distribution?
There are 3 correct answers to this question.
Response:
Which of the following business processes can be mapped in Sales and Distribution?
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D
Vote an answer
Which account category is used for account assignment of orders, which includes network headers, network activities, maintenance orders, internal orders and manufacturing orders?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Vote an answer
In which type of settlement the costs of all the periods up to the one you specify in settlement are settled?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Vote an answer
Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity?
Please choose the correct answer.
Response:
Capacity planning board
Please choose the correct answer.
Response:
Capacity planning board
Correct Answer: C
Vote an answer
Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element.
Which of the following costs can be planned?
There are 3 correct answers to this question.
Response:
Which of the following costs can be planned?
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,D
Vote an answer
Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Vote an answer