Due to unpredictable material tariffs, a campus project anticipates possibly changing its structural framing system once pricing is finalized. This could affect floor-to-floor heights across several buildings.
What method would best ensure both initial and ongoing coordination of Levels and Grids across a large multidisciplinary Revit project?
What method would best ensure both initial and ongoing coordination of Levels and Grids across a large multidisciplinary Revit project?
Correct Answer: D
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
Which of the following would typically be included in an AECO BIM data handover package at project closeout?
Correct Answer: A
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
A design team is distributing models to a construction team's coordinator, who reports that the various models are not aligned to each other when linked into the coordination environment.
What step should the design team's lead BIM manager take to resolve the positioning issue?
What step should the design team's lead BIM manager take to resolve the positioning issue?
Correct Answer: B
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
When working with separate Revit templates for each discipline, which elements should be standardized to support collaboration and seamless coordination across the project?
Correct Answer: C
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
A project team has been ignoring their model warnings, and from talking with the team, it is apparent that they are intimidated by the number of warnings and unwilling to tackle resolving them.
What steps can the BIM manager take to educate the team and alleviate their reluctance to address these issues?
What steps can the BIM manager take to educate the team and alleviate their reluctance to address these issues?
Correct Answer: A
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
The BIM manager is coordinating a multi-building project in which each building must maintain a unique internal coordinate system but share a common origin point for site-wide references.
Which two actions are required to correctly manage the coordinate setup in this scenario? (Select two.)
Which two actions are required to correctly manage the coordinate setup in this scenario? (Select two.)