Oracle Project Management Cloud 2020 Implementation Essentials - 1z0-1057-20 Exam Practice Test
You create a project schedule with a Shifts element. Identify two more elements that can be part of a project schedule. (Choose two.)
Correct Answer: B,D
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
In a Project Draft Invoice preview, quantity (hours) and unit price (bill rate) are shown as fields on the invoice.
Quantity and unit price are then used to calculate the line total, then the total price of the invoice. After the invoice is transferred or created in Receivables, the invoice detail has a quantity of 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.
Identify the correct statement about details in the receivables invoice. (Choose the best answer.)
Quantity and unit price are then used to calculate the line total, then the total price of the invoice. After the invoice is transferred or created in Receivables, the invoice detail has a quantity of 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.
Identify the correct statement about details in the receivables invoice. (Choose the best answer.)
Correct Answer: C
Vote an answer
Your customer wants additional project information for detailed account balance maintenance, reconciliation, and reporting. Identify the configuration in subledger accounting that can be set up to fulfill this requirement.
(Choose the best answer.)
(Choose the best answer.)
Correct Answer: C
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
Select two correct statements about project classifications on a template. (Choose two.)
Correct Answer: B,C
Vote an answer
You are now the project manager of a newly created implementation project. Which two items are not part of managing an implementation project?
Correct Answer: D,E
Vote an answer
After completing setups in a source environment, your customer wants to move the setup data to a target environment. Identify the two statements related to task list scope, which you must consider before taking a decision based on the customer requirement. (
Correct Answer: B,C
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
Your customer started operations and all projects in January 2015. They implemented Enterprise Project Structure for calculating project labor demand by using the Annual option. When they view the labor demand on 15-Dec-2015, the project hierarchy viewer shows data only for the year 2015. The client expected the demand to be shown for a year, from 15-Dec-2015 to 15-Dec-2016.
Identify how the project hierarchy viewer displays labor demand information. (Choose the best answer.)
Identify how the project hierarchy viewer displays labor demand information. (Choose the best answer.)
Correct Answer: A
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
Your customer wants to generate accounting based on project information associated with the transaction for all subledger transactions. Identify three subledger applications for which the project source is available for deriving accounts when configuring subledger accounting. (Choose three.)
Correct Answer: B,C,D
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).
Your business user has created a purchase order (PO) that has the following attributes:
Accrue at Receipt = Yes
Matching Option = 2 way
Receipt Close Tolerance = 100%
After approval, the PO is closed for receiving without creating a receipt. An AP invoice is created by matching to the PO. The user now runs Create Accounting for Receiving Transactions and then the "Import and Process Cost transactions" ESS (Enterprise Scheduler Service) job using the Transaction Source parameter as "Oracle Payables". The user notices that there is no cost transferred to the projects. Identify two reasons for this problem. (Choose two.)
Accrue at Receipt = Yes
Matching Option = 2 way
Receipt Close Tolerance = 100%
After approval, the PO is closed for receiving without creating a receipt. An AP invoice is created by matching to the PO. The user now runs Create Accounting for Receiving Transactions and then the "Import and Process Cost transactions" ESS (Enterprise Scheduler Service) job using the Transaction Source parameter as "Oracle Payables". The user notices that there is no cost transferred to the projects. Identify two reasons for this problem. (Choose two.)
Correct Answer: A,D
Vote an answer
Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio Management and Oracle Project Portfolio Management Cloud. (Choose three.)
Correct Answer: A,D,E
Vote an answer
Explanation: Only visible for PassTestking members. You can sign-up / login (it's free).