How does agile address the risk associated with the project not being fully understood at the beginning?
Suggested Answer: C Vote an answer
by kengichuhi at Nov 24, 2025, 08:59 AM
Comments
kengichuhi
2025-11-24 08:59:39C. By preventing the analysis of details at the start → This suggests that analysis is blocked entirely, which is not true in Agile. Agile doesn’t prevent analysis; it encourages just enough analysis at the right time.
B. By avoiding too much detail at the start → This is more accurate. Agile allows some initial analysis to start work, but avoids over-specifying requirements before the project evolves.