Exam PRINCE2-Agile-Foundation Topic 4 Question 77 Discussion

Actual exam question for PRINCE2's PRINCE2-Agile-Foundation exam
Question #: 77
Topic #: 4
How does agile address the risk associated with the project not being fully understood at the beginning?

Suggested Answer: C Vote an answer

by kengichuhi at Nov 24, 2025, 08:59 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
kengichuhi
2025-11-24 08:59:39
Best answer B.
C. By preventing the analysis of details at the start → This suggests that analysis is blocked entirely, which is not true in Agile. Agile doesn’t prevent analysis; it encourages just enough analysis at the right time.

B. By avoiding too much detail at the start → This is more accurate. Agile allows some initial analysis to start work, but avoids over-specifying requirements before the project evolves.
upvoted 1 times
...
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.