Exam PMP Topic 1 Question 196 Discussion

Actual exam question for PMI's PMP exam
Question #: 196
Topic #: 1
The following is a network diagram for a project.

The shortest non-critical path for the project is how many days in duration?

Suggested Answer: A Vote an answer

Section: Planning

by Curitis at May 25, 2026, 02:42 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.