A PMO professional is acting as the PMO leader temporarily in a well-established and mature PMO unit. In this role, a PMO professional receives an escalation from the portfolio manager that a new business stakeholder's activity is overlapping with key portfolio management functions.
What should the PMO professional do to resolve this issue?
What should the PMO professional do to resolve this issue?
Suggested Answer: B Vote an answer
The PMO charter defines the PMO's roles, responsibilities, and boundaries. PMI-PMOCP stressesreviewing the charter with involved partiesto clarify roles and resolve overlaps or conflicts, reinforcing governance and accountability.
Training on values (A), conflict resolution codes (C), or project charters (D) are less direct for resolving PMO governance overlap issues.
Reference:PMI-PMOCP Study Guide, Chapter on Governance and PMO Charter.
Training on values (A), conflict resolution codes (C), or project charters (D) are less direct for resolving PMO governance overlap issues.
Reference:PMI-PMOCP Study Guide, Chapter on Governance and PMO Charter.
by Beverly at Jan 03, 2026, 05:45 PM
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).