SAP Certified Application Associate – SAP S/4HANA Production Planning and Manufacturing (1809) - C_TS420_1809 Exam Practice Test

Which functional capabilities does the Detailed Scheduling Board have?
There are 2 correct answers to this question.
Response:
Correct Answer: B,D Vote an answer
What are drawbacks of the separation of OLTP and OLAP?
There are 4 correct answers to this question.
Response:
Correct Answer: A,B,C,E Vote an answer
What new technology is used in SAP S/4HANA Embedded Analytics?
Please choose the correct answer.
Response:
Correct Answer: D Vote an answer
Which reports can you access via the order and resource reporting transaction in advanced planning?
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,D Vote an answer
What Kanban status automatically posts goods receipt with reference to the procurement element?
Please choose the correct answer.
Response:
Correct Answer: D Vote an answer
How can you avoid order proposals for planned independent requirements with dates in the past?
There are 2 correct answers to this question.
Response:
Correct Answer: A,B Vote an answer
At the end of the MRP run you receive the exception message "Reschedule In Operation". What caused the message to be generated?
Please choose the correct answer.
Response:
Correct Answer: D Vote an answer
What are the three transition scenarios for an S/4HANA implementation?
There are 3 correct answers to this question.
Response:
Correct Answer: A,D,E Vote an answer
What are pillars of SAP Activate?
There are 2 correct answers to this question.
Response:
Correct Answer: A,B Vote an answer
What are some of the advantages of using Kanban?
There are 2 correct answers to this question.
Response:
Correct Answer: C,D Vote an answer